Turnkey 008

Spinnaker Exploration High Island 235



  • OSFI was responsible for the engineering, design, procurement, fabrication and installation of this caisson production deck
  • This job was installed 11 weeks after contract signing
  • The deck and production facility were taken from OSFI’s stock inventory
 
  • Caisson Production Deck
  • Single Well
  • 35 MMSCFD Production Facility
  • 10 Week Fabrication Schedule
  • Installed mid April 1999

 
 
 
 