- Tripod Platform
- 6 Wells
- 40 MMSCFD Production
- 11 Week Fabrication Schedule
- 131' Water Depth
|
- OSFI was responsible for the design, procurement, fabrication and installation
- The deck and the production facilities were OSFI’s standard design, taken out of our turnkey inventory
|